⚠ Construction Public Notice

2800 Telegraph

Berkeley, CA 94704
Project Type 6-Story Residential
Total Units 17 Apartments
Expected Completion Q3 2028
🏗

Project Description

Construction of a 6-story building.

🔧

Construction Activities

Major phases of construction include the following:

  • Demo of existing building and hardscape
  • Excavation and grading to follow for preparation of the building foundation
  • Underground utilities
  • Forming and subsequent pouring of concrete foundation and podium
  • Five stories of vertical framing including exterior and interior building finishes
  • Site improvements including landscape, sidewalks, etc.
  • Daily construction activities: use of hand tools (hammer, drills, etc.), hauling and hoisting of material, construction equipment such as backhoes, reach lifts, compressors, etc.
📅

Anticipated General Schedule

July – Sept 2026
Demo, Grading & Utilities
Sept – Oct 2026
Concrete Construction
Oct 2026 – Mar 2027
Framing
Mar 2027 – Feb 2028
Façade and Finishes
Jan 2028 – Mar 2028
Site Improvements, Landscaping, Sidewalks

Daily Construction Schedule

Weekdays Mon – Fri, 8:00 AM – 5:00 PM
Saturday (If Needed) 10:00 AM – 3:00 PM
Expected Start
July 2026
|
Expected Finish
Q3 2028
📞

Noise Management Contact

👤
Noise Management
Avi Forman
📄